VSM Fundamentals

VSM diagrams map the current state and future state of material and information flow:

┌─────────┐                                         ┌──────────┐
│ Supplier │──── Material Flow ──────────────────────►│ Customer │
└─────────┘                                         └──────────┘
     │              ┌─────┐    ┌─────┐    ┌─────┐        ▲
     └──────────────► P1  ├────► P2  ├────► P3  ├────────┘
                    │C/T  │    │C/T  │    │C/T  │
                    │C/O  │    │C/O  │    │C/O  │
                    │Avail│    │Avail│    │Avail│
                    └──┬──┘    └──┬──┘    └──┬──┘
                       │          │          │
  ◄────────────────── Information Flow ──────────────────────┐
                                                              │
  Timeline: NVA ─── VA ─── NVA ─── VA ─── NVA ─── VA       │
            wait    work   wait    work   wait    work      PLT

Core VSM elements:


UBML → VSM Mapping

Value Stream Structure

VSM Element UBML Concept Mapping Quality Notes
Value stream (overall) ValueStream ✅ Full Direct 1:1 mapping. Name, description, owner.
Customer ValueStream.customer (ActorRef) ✅ Full The end beneficiary.
Supplier (no direct field) ◐ Partial Could use ValueStream.triggeringEvent or an Actor reference. No dedicated supplier field.
Triggering event ValueStream.triggeringEvent ✅ Full “Customer places order”, “Raw material arrives”.
Ending event ValueStream.endingEvent ✅ Full “Product delivered”, “Payment received”.
Value outcome ValueStream.valueOutcome ✅ Full “Customer receives working product on time”.

Process Boxes

VSM Element UBML Concept Mapping Quality Notes
Process box ValueStream.stages[].processesProcess ✅ Full Each stage contains references to detailed processes.
Stage name ValueStream.stages[].name ✅ Full Stage label.
Cycle time (C/T) Step.duration ◐ Partial Duration exists on steps, not on value stream stages. Must aggregate from referenced processes.
Changeover time (C/O) (no equivalent) ✗ Gap No changeover/setup time concept.
Uptime / Availability (no equivalent) ✗ Gap No machine/process availability percentage.
Batch size (no equivalent) ✗ Gap No batch/lot size. Closest: Scenario.arrivals for arrival patterns.
Number of operators ResourcePool.capacity ◐ Partial Resource pools define headcount in scenarios, not on the value stream itself.
Scrap/rework rate Link.probability on error paths ◐ Partial Rework loops with probabilities, but not as a process-box metric.

Material & Information Flow

VSM Element UBML Concept Mapping Quality Notes
Material flow (push) Link (between steps/processes) ◐ Partial UBML links model control flow. Material vs. information flow isn’t distinguished.
Material flow (pull) (no equivalent) ✗ Gap No push/pull production control concept.
Inventory triangle (WIP) (no equivalent) ✗ Gap No inter-process inventory quantity. ResourcePool.wipLimit limits concurrent work on a resource, not stock between processes.
Supermarket (kanban buffer) (no equivalent) ✗ Gap No kanban/buffer concept.
FIFO lane (no equivalent) ✗ Gap No queue discipline concept (see also BPSim gaps).
Electronic info flow Step.messages / ProcessCall ◐ Partial Cross-process communication exists but isn’t typed as electronic/manual.
Manual info flow Step.kind: handoff ◐ Partial Handoffs imply human-mediated information transfer.
Production control (no equivalent) ✗ Gap No scheduling/production control entity in UBML.

Timeline & Metrics

VSM Element UBML Concept Mapping Quality Notes
Production Lead Time (PLT) KPI (on value stream) ◐ Partial Can be modeled as a KPI with formula. Not calculated from the map.
Value-added time (no classification) ✗ Gap Steps don’t classify as VA/NVA/NNVA.
Non-value-added time (waste) (no classification) ✗ Gap Same — no waste classification per step.
Process cycle efficiency KPI.formula ◐ Partial Can define PCE = VA time / PLT as a KPI, but values aren’t computed.
Takt time KPI or Scenario.arrivals ◐ Partial Customer demand rate. Can be modeled in scenarios.

Improvement & Future State

VSM Element UBML Concept Mapping Quality Notes
Kaizen burst Insight (type: recommendation) ✅ Full Improvement opportunities captured as insights with source traceability.
Kaizen burst HypothesisNode (recommendation) ✅ Full Structured improvement proposals in hypothesis trees.
Future state map Scenario (variant) ✅ Full Scenarios model proposed changes with impact analysis.
Implementation plan (no equivalent) ✗ Gap No project management / implementation timeline. See DATA-FORMATS.md MS Project gaps.

UBML Information Lost on VSM Export

UBML Concept Why Lost
Block operators (par/alt/opt/loop) VSM shows a linear material flow; control flow branching doesn’t exist
Decision steps, gateways VSM processes don’t branch — every unit flows through every process
RACI assignments VSM shows operator count, not role-based assignments
Entity model (attributes, relationships, lifecycle) VSM data objects are implicit in material flow
Knowledge layer (sources, insights) VSM captures kaizen opportunities, not knowledge provenance
Hypothesis trees / SCQH VSM is operational, not analytical
Approval/review gates, notifications Not part of VSM notation
Actor hierarchy, personas Operators are headcount, not organizational structure
Process hierarchy (L1–L4) VSM is always one level — the value stream level
Scheduling dependencies (FS/SS/FF/SF) Processes flow sequentially by material movement

VSM Concepts UBML Cannot Capture

Production Control (High Impact)

VSM Concept Description UBML Gap
Push vs. Pull Fundamental VSM distinction: does upstream push work or does downstream pull it? Push = overproduction risk. Pull = demand-driven. Arrows are differently styled. UBML links have no push/pull semantics. All flow is structural (“this step leads to that step”), not production-control-typed.
Kanban (supermarket) Pull-based inventory buffer between processes. Downstream withdraws; upstream replenishes. Limited WIP by design. No buffer/inventory entity between processes. ResourcePool.wipLimit limits work on a resource, not stock between process stages.
FIFO Lane First-in-first-out queue between processes ensuring order preservation. No queue discipline (see also BPSim gaps in DATA-FORMATS.md).
Production scheduling / leveling (heijunka) Smoothing production to match takt time. Leveling box visualization. No production scheduling concept. UBML’s scheduling is dependency-based (FS/SS/FF/SF), not leveling-based.
Pacemaker process The single process that sets the pace for the entire value stream. Only the pacemaker is scheduled; upstream pulls from it. No concept of a pacemaker. All UBML processes are structurally equivalent.

Severity: High. Push/pull and kanban are the core analytical framework of VSM. Without them, a UBML model can describe what happens but not how production is controlled — which is VSM’s entire reason for existence.

Waste & Time Classification (High Impact)

VSM Concept Description UBML Gap
7 Wastes (muda) Overproduction, waiting, transport, over-processing, inventory, motion, defects. Each step/transition is classified. UBML steps have duration and effort but no waste classification. Pain points in personas capture waste narratively but not as step-level metrics.
VA / NVA / NNVA classification Every activity classified as Value-Added, Non-Value-Added (eliminate), or Non-Value-Added but Necessary (minimize). No classification enum on steps. This is the fundamental analytical dimension of VSM.
Timeline bar Visual separation of VA time (bottom) from NVA time (top/waiting). Total Lead Time vs. Value-Added Time comparison. No timeline bar concept. KPIs can compute ratios, but the visual timeline is a rendering concern.
Process Cycle Efficiency PCE = Value-Added Time ÷ Total Lead Time. The headline metric of every VSM. Can be modeled as a KPI.formula but UBML doesn’t compute it from step data.

Severity: High. VA/NVA classification is what makes a value stream map analytical rather than just a process flow. Without it, UBML’s ValueStream is a structural description, not an analytical tool.

Physical Manufacturing Concepts (Medium Impact)

VSM Concept Description UBML Gap
Inventory triangles WIP counts between processes. Measured in units or days of supply. No inter-process inventory model. UBML entities are information objects, not physical stock.
Changeover time (C/O) Time to switch equipment from one product type to another. A key lean metric — high C/O drives large batch sizes. No changeover concept. Step.duration is processing time per unit.
Uptime / Availability % Percentage of scheduled time a process/machine is actually available. No availability concept on processes or resources.
Batch size Number of units processed together before moving to next step. No batch concept. UBML processes model single-unit flow logic.
Distance / transport Physical distance between process steps. Transport is a waste category. UBML Location has coordinates but process steps don’t reference locations to compute distances.
Operator count per process Headcount working at each process step. ResourcePool.capacity in scenarios, but not on value stream stages directly.

Severity: Medium. These are critical for manufacturing VSM but less relevant for service/office value streams, where UBML’s primary audience operates.

Current State vs. Future State Formalism (Low Impact)

VSM Concept Description UBML Gap
Current State Map Formal “as-is” document with observed data (timed, counted). UBML doesn’t distinguish current-state from future-state models structurally. File organization (folders) or scenario variants handle this, but there’s no schema-level distinction.
Future State Map Proposed state with kaizen improvements applied, projected metrics. UBML Scenario variants model future states. The mapping is good but VSM’s convention of paired maps (current + future side by side) isn’t built into UBML.
Implementation timeline Prioritized kaizen events with owners and deadlines. No project management model (see MS Project gaps in DATA-FORMATS.md).

Rendering Considerations

VSM has a highly standardized visual vocabulary (icons from “Learning to See” by Rother & Shook). UBML export to VSM format would need to render:

VSM Symbol What It Represents Rendering Source
Process box Stage with metrics ValueStream.stages + referenced Process KPIs
Inventory triangle WIP between stages (not available from UBML data)
Push arrow Material pushed downstream (not available)
Pull circle Kanban withdrawal (not available)
Supermarket Buffer inventory (not available)
Kaizen burst Improvement opportunity Insights/Hypotheses linked to stages
Customer/Supplier icon External parties ValueStream.customer, Actor references
Information flow (zigzag) Electronic data ProcessCall, messages
Information flow (straight) Manual data Step.kind: handoff
Timeline VA / NVA times (requires step VA/NVA classification)
Data box C/T, C/O, uptime, batch Step.duration + (gaps for C/O, uptime, batch)

Practical recommendation: For full VSM rendering, UBML would need:

  1. A wasteClassification enum on steps (VA, NVA, NNVA) — or equivalent annotation
  2. Inter-process inventory/WIP data
  3. Process-level metrics (C/T, C/O, uptime) beyond Step.duration

Until then, UBML can generate a structural value stream diagram (stages, flow, parties) but not a metrics-rich VSM with the analytical power Lean practitioners expect.


Import Considerations (VSM → UBML)

VSM Element UBML Import Strategy
Value stream Import as ValueStream with name, customer, trigger, outcome
Process boxes Import as stages referencing detailed Process documents
Cycle time Import as Step.duration on process steps
Changeover time Import as custom field — no native property
Inventory Import as custom field on links between processes
Push/pull Import as custom field or annotation
Kaizen bursts Import as Insight (type: recommendation) with source ref
Future state Import as Scenario variant
VA/NVA classification Import as custom field or tag on steps
Operator count Import as ResourcePool.capacity in scenario
Timeline metrics (PLT, VA time) Import as KPI on value stream

See README.md for the full projection index and information loss matrix.